With our confidential Gigawatts level project ongoing but not announced, I needed to keep quiet until it was announced a few days ago.
🤔?
First, the pivot. Our two Texas projects are Duval County and Zapata County, each 1 GW. Duval County, Texas, 1 GW, about 537 acres, received a conditional Studied Load Firm classification under ERCOT's Batch Zero process, with expected energization in Dec. 2028. Zapata County, Texas, 1 GW pipeline, about 290 acres, pending ERCOT Batch Study, with expected energization in Dec. 2029.
一企業でやるなら大きな話だが、二つとも上手く行くかは別だよね?🫣
とりあえず最初の案件だけでも成功させてから大きな事を言わないとね、経営陣は🤔
投資の参考になりましたか?